Klong Dan Waste Water Treatment Plant

Govt to seek retrial of Klong Dan case

Date of Release: 
May 17 2016

THE Cabinet resolved yesterday to seek an Administrative Court retrial in the corruption-plagued Klong Dan wastewater treatment plant case, in which the government was ordered to pay Bt9.6-billion compensation to the contractors for cancelling its construction.

The Finance Ministry was assigned by the Cabinet to approach the court again, Government Spokesman Maj-General Sansern Kaewkamnerd said yesterday.

The government would attempt to prove that the NVPSKG consortium of contractors had distorted facts and been instrumental in the irregularity involving state officials.

«

Officials face Klong Dan rap

Date of Release: 
Nov 19 2015

Officials found to be involved with the scandal-hit Klong Dan waste water treatment plant in Samut Prakan will be held responsible for huge fees incurred by the government for breach of contract.

They will have to cover the nine-billion-baht penalty which the government has been ordered to pay to the contractor, said Ministry of Natural Resources and Environment permanent secretary Kasemsun Chinnavaso.

Mr Kasemsun said Wednesday that a committee has been set up to investigate officials who were involved in the corruption saga.

«

Punish Klong Dan cheaters

Date of Release: 
Nov 19 2015

The cabinet on Tuesday approved a budget of 9.8 billion baht to be disbursed from the Central Fund for the Ministry of Natural Resources and Environment to pay the NVPSKG consortium for the construction of the Klong Dan waste water treatment project in Samut Prakan province as ordered by the Administrative Court.

«